NNPC Starts Rehabilitation Of Port Harcourt Refineries

Nigerian National Petroleum Corporation (NNPC) said it has commenced the revamping of the two refineries in Port Harcourt in its bid to ensure local sufficiency in refined petroleum products.
In a statement by the corporation's spokesman, Ndu Ughamadu, the rehabilitation of the refineries is coming 19 years after the last Turn Around Maintenance (TAM) exercise of the nation’s premier refining plant.  
He said the NNPC is embarking on the first phase of the rehabilitation of the 210,000 barrels per day capacity Port Harcourt Refinery complex that comprises the 60,000 barrels per day old Refinery built in 1965 and the 150,000 barrels per day, new Refinery, commissioned in 1989.
Ughamadu said the project would be executed by Milan-based Maire Tecnimont S.p.A, in collaboration with its Nigerian affiliate, Tecnimont Nigeria.
Maire Tecnimont S.p.A is listed on Milan Stock Exchange with interest in international engineering and construction, technology and licensing, and energy business development, while the Tecnimont group had operations in 40 different countries, numbering about 50 operative companies with a workforce of about 5,500 employees.
The rehabilitation of the refineries would help to boost their capacity to about 60 percent capacity utilization.
Ughamadu said NNPC was engaging eni/NAOC as Technical Advisor to support the Rehabilitation of PHRC, saying NNPC/PHRC would leverage eni’s extensive refinery supply chain network and warehouses to procure critical materials for the programme.
He noted that this first phase of the rehabilitation contract which would run for six months will involve detailed integrity check and equipment inspection of the Port Harcourt Refinery complex beginning from end of March, 2019.
The integrity test comes as a forerunner to the second phase of the rehabilitation project which entails a comprehensive revamp of the complex aimed at restoring the refinery to a minimum of 90 percent capacity utilization.
Subject to the successful completion of the integrity checks, Phase 2 of the project would be executed on an Engineering Procurement Construction basis by Tecnimont in collaboration with the original builders of the plant, JGC of Japan.